Corridor Implementation Status

Real-time engineering progress across elevated viaducts, underground tunneling, track laying, and traction power.

42 km Operational & Growing

Section-Wise Commissioning Progress

The 82.15 km Delhi-Ghaziabad-Meerut corridor is advancing rapidly in phased stages toward full commercial operations.

OPERATIONAL 100% Complete

Priority & Expanded Section

Route: Sahibabad to Meerut South (42 km)
Stations: 8 Stations Active (Sahibabad, Ghaziabad, Guldhar, Duhai, Duhai Depot, Murad Nagar, Modi Nagar South, Modi Nagar North, Meerut South).

Commuter Services Active
ADVANCED CIVIL & TRACK 94% Complete

Delhi Section (Underground & Elevated)

Route: Sarai Kale Khan to Anand Vihar to New Ashok Nagar (14 km)
Key Milestones: 100% tunneling completed under Yamuna River bed; Anand Vihar underground station civil work completed; OHE and signaling trials underway.

Testing & Commissioning
FINAL STAGE 88% Complete

Meerut Section (RRTS + MRTS)

Route: Meerut South to Modipuram (23 km)
Key Milestones: Underground tunneling through dense old Meerut completed; Meerut Central and Bhaisali underground stations finishing architectural work; local Meerut Metro 3-car rakes delivered to Modipuram depot.

Finishing & Systems

Engineering Highlights by the Numbers

100%

Tunneling Completed

3,000+

Pillars Erected

100%

Make in India Rakes

ETCS-2

LTE Hybrid Signaling